This development comprises 12 No. 4bedroom semi detached duplex dwellings to be built on one acre of land on Adebayo Doherty Road in the first phase of the Lekki Peninsula scheme.
The client is a developer called Eco-Building Systems Limited, who erect panelised pre-fabricated homes made of fiber reinforced cement panels on a galvanized steel framework.
Construction work started in mid April 2003 and was commissioned on the 25 th March 2004. All of the 12 units are ready for occupation.
|